Title: PM3 Project Modifications for Coral Reef Elementary Recommendation:
I recommend the School Board ratify Project Modifications in the amount of $158,137.00 for Coral Reef Elementary School, Class Size Reduction Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description:
Coral Reef Elementary School – Class Size Reduction Project #2581-8950
This project modification contains the following item:
- CCD #1 in the amount of $158,137.00.
- Description: Provide all necessary labor, materials, bonds and insurance necessary to revise existing bus loop and additional parking, and install an additional access lane for the parent drop-off/pick-up.
- Cause: School District Requested.
- Justification: The existing bus loop radius was too small. Buses crossed the curb on both sides of the drive and created a safety hazard. Additional parking, located in an island at the bus loop is required for the new staffing of the additional classrooms. The total cost of this work is $419,785.00. An allowance of $261,648.00 was included in the GMP. The difference between the Allowance in the GMP and the actual cost is $158,137.00.
Financial Impact:
The financial impact to the Project's Budget is $158,137.00.
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
PM3 Site Plan.pdf
PM3 Data Panel.pdf
PM3 Backup.pdf
Perfect Commerce Agreement.pdf
Q&APM3.doc
|