New Business - Purchasing/Construction

Title: CP-2 GMP Amendment for Lake Worth MS Classroom Addition

Recommendation:

I recommend the School Board revise the project budget to $8,817,924 and approve an Amendment to the Construction Management at Risk Agreement to establish the Final Guaranteed Maximum Price (GMP) for construction in the amount of $6,989,651 to Kaufman Lynn inc., General Contractors for Lake Worth Middle School, Project No. 2131-8307 and authorize the Superintendent and Board Chairman to sign all required documents. 

Description:

Construction Management @ Risk Services required for construction of a 346 student station addition at Lake Worth Middle School in accordance with permitted design documents and the Educational Specifications approved by the Board on June 7, 2006.

 

Estimated Construction Budget:  $6,622,700.

 

No. of Stories: Two

Construction Type: Tilt-Wall

Gross Square Feet: 33,330

Budgeted Construction Cost per Gross Square Foot: $198

Actual Total Construction Cost per Gross Square Foot: $211

Building Cost: (Div. 3-16) $6,090,955.

Actual Building Cost per Gross Square Foot: (Div. 3-16) $182

Student Stations: 346

Budgeted Construction Cost per Student Station: $19,140.

Actual Construction Cost per Student Station: (Div. 3-16) $20,331.

 

Preconstruction Fee:                  $45,115.          

 

GMP:                                     $6,989,651.    

 

Total Cost of Construction:  $7,034,766.     

Minority Sub-Contractor Participation:   22.87%  

Financial Impact:

The financial impact is an increase to the project budget of $590,338., and a commitment of $7,041,284 which includes the GMP of $6,989,651 and $51,723 for the District provided Builder’s Risk Insurance. The source of funds is the corresponding Capital Projects Budget. The source of the additional funds is the Restricted Reserve.  

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)

Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)

Attachments (list):
LWMS - Budget Revision.pdf
Beneficial.pdf
PPE.pdf
EdSpec.pdf
DataPanel.pdf
SITE PLAN.pdf
ExeAgreeLWMS.pdf
FirmExeAmend.pdf
Exhibit B.pdf
GMP PROPOSAL.pdf
legal Checklist.pdf

spacer graphic