New Business - Purchasing/Construction

Title: CP-3 GMP Amendment for Okeeheelee MS Classroom Addition

Recommendation:
I recommend the School Board revise the project budget to $9,529,191. and approve an Amendment to the Construction Management at Risk Agreement to establish the Final Guaranteed Maximum Price (GMP) for construction in the amount of $7,448,689. to Kaufman Lynn Inc., General Contractors for Okeeheelee Middle School, Project No. 2151-8307 and authorize the Superintendent and Board Chairman to sign all required documents.

Description:

Construction Management at Risk Services required for construction of a classroom addition consisting of 286 student stations for class size reduction and 186 student stations for programs in accordance with Educational Specifications approved by the Board March 15, 2005.

 

Estimated Construction Budget:  $7,144,267.   

                                                                        

No. of Stories: Two

Construction Type: Tilt-Wall

Gross Square Feet: 40,689

Budgeted Construction Cost per Gross Square Foot: $192

Actual Total Construction Cost per Gross Square Foot: $186

Building Cost: (Div. 3-16) $6,929,517.

Actual Building Cost per Gross Square Foot: (Div. 3-16) $170

Student Stations: 454

Budgeted Construction Cost per Student Station: $15,736.

Actual Construction Cost per Student Station: (Div. 3-16) $16,656.

Preconstruction Fee:                      $56,062.

CCD #1                                          $57,111.

GMP:                                        $7,448,689.

 

Total Cost of Construction:      $7,561,862.     

 

Building Cost:                          $6,929,517.

Minority Sub-Contractor Participation:  19.6 %   

Financial Impact:

The financial impact is an increase to the project budget of $654,325. and a commitment of $7,503,808. which includes $7,448,689. for the GMP and $55,119. for the District provided Builder’s Risk Insurance. The source of the additional funds is the 2007 Capital Contingency.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)

Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)

Attachments (list):
BudgetRevJC.pdf
BENEFICIAL.pdf
PPE.pdf
ED SPecOkee.pdf
Data Panel OkeeMS.pdf
ConecpSiteOkee.pdf
ExeAgreeKLOkee.pdf
GMP PROPOSAL.pdf
GMP AMEND.pdf
Legal Checklist.pdf

spacer graphic