Construction Management @ Risk Services required for Preconstruction Phase Services including design review and recommendation to establish a Guaranteed Maximum Price for construction of  a 38,658 GSF building to accommodate 112 student stations for new academy programs and 375 student stations for class size reduction. Construction will be in accordance with the Educational Specifications approved by the Board on October 10, 2004.
 
Estimated Budget for Construction:  $11,613,967
  
Construction Type: To be determined during Preconstruction Phase
No. of Stories: To be determined during Preconstruction Phase. 
Gross Square Feet: 38,658
Estimated Construction Cost/Gross Square Foot: $300
Total New Student Stations: 487
Estimated Construction Cost/Student Station: $23,847
 
Preconstruction Phase Services Fee:   $106,920
Reimbursable Expenses:                       $20,310
 
Total:                                                    $127,230
 
Three (3) firms responded to the RFP and all three (3) were shortlisted.  The final ranking of the Selection Committee is as follows:  
 
(1) The Weitz Company I, Inc.
(2) Moss & Associates 
(3) Catalfumo Construction Ltd. 
 
Minority Sub-consultant Participation: 20.22%