| 
						 Title: PM2 PBG Area ES (03-X) Project Modifications Recommendation: 
I recommend the School Board ratify Project Modifications in the amount of $238,750.00 for Palm Beach Gardens Elementary School, New School Project #0661-8337, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description: This project modification contains the following item: 
  
Item #1  
- CCD #1 in the amount of $238,750.00 
 - Description: Tilt wall contractor withdrawal 
 - Cause: School District Requested 
 - Justification: The tilt wall contractor (Woodland Construction) chose not to participate in the mandatory MCIP (Master Controlled Insurance Program). The work was self-performed by Design Build contractor (Pirtle).  The project was awarded in October 2005, which was prior to the establishment of the District's MCIP.  
   
Financial Impact: 
The Financial Impact to the Project’s Budget is $238,750.00. 
  
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches 
Attachments (list): 
03-X PBG Area ES Budget History.pdf 
03-X PBG Area ES Site Plan.pdf 
03-X PBG Area ES Facility List.pdf 
						 
					 |