Title: PM2 PBG Area ES (03-X) Project Modifications Recommendation:
I recommend the School Board ratify Project Modifications in the amount of $238,750.00 for Palm Beach Gardens Elementary School, New School Project #0661-8337, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: This project modification contains the following item:
Item #1
- CCD #1 in the amount of $238,750.00
- Description: Tilt wall contractor withdrawal
- Cause: School District Requested
- Justification: The tilt wall contractor (Woodland Construction) chose not to participate in the mandatory MCIP (Master Controlled Insurance Program). The work was self-performed by Design Build contractor (Pirtle). The project was awarded in October 2005, which was prior to the establishment of the District's MCIP.
Financial Impact:
The Financial Impact to the Project’s Budget is $238,750.00.
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
03-X PBG Area ES Budget History.pdf
03-X PBG Area ES Site Plan.pdf
03-X PBG Area ES Facility List.pdf
|