						 Title: Amend the CM Agreement for Carver MS Recommendation: 
I recommend the School Board revise the project budget from $5,618,340 to $8,287,642. and approve an Amendment to the Construction Management at Risk Agreement to establish the Final Guaranteed Maximum Price (GMP) for construction in the amount of $6,653,537.20 to Horus Construction Services INC. /Greater Bay Construction Company, INC., A Joint Venture, for Carver Middle School Classroom Addition, Project No. 2041-8307 and authorize the Superintendent and Board Chairman to sign all required documents.    
Description: Construction Management @ Risk Services required for construction of a 29,807 GSF, 317 student station addition at Carver Middle School, in accordance with the Educational Specifications approved by the Board on June 7, 2006. This project is a program addition, and is intended to eliminate portable classrooms and meet the needs of existing programs of the school.  
  
Estimated Construction Budget: $4,522,764. (5-Year Capital Plan) 
                                         
  
Number of Stories: 2 
Construction Type: Masonry 
  
Gross Square Feet: 29,807 
Budgeted Construction Cost per Gross Square Foot: $ 152 
Actual Total Construction Cost per Gross Square Foot: $225 
Building Cost per Gross Square Foot (Div. 3-16): $162 
  
Student Stations: 317 
Budgeted Construction Cost per Student Station: $14,267. 
Actual Construction Cost per Student Station (Div. 3-16): $21,152. 
Building Cost per Student Station: $15,255. 
  
Preconstruction Fee:                     $51,500.00 
GMP:                                       $6,653,537.20 
  
Total Cost of Construction:     $6,705,037.20 
  
Building Cost (Div. 3-16):      $4,835,773 
  Minority Sub-consultant Participation:     27 %  
Financial Impact: 
The financial impact is an increase the project budget of $2,669,302 and a commitment of $6,702,269 which includes the GMP of $6,653,537.20 and the District provided Builder’s Risk Insurance of $49,232.  The source of funds is the corresponding Capital Projects Budget. The source of the additional funds is from Restricted Reserve. 
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us)  
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)  
Attachments (list): 
BudgetRev.pdf 
Beneficial.pdf 
PPE.pdf 
edspecCarver.pdf 
Carver MS.pdf 
siteplan.pdf 
Agreement.pdf 
GMP PROPOSAL.pdf 
Amendment Carver.pdf 
Checklist.pdf 
						 
					 |