						 Title: PM3 Liberty Park Elementary Project Modifications Recommendation: 
I recommend the School Board ratify Project Modifications in the amount of $56,966.00 for Liberty Park Elementary School, Classroom Addition Project #1871-8376, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description: This project modification contains the following item: 
  
- CCD #2 in the amount of $56,966.00. 
 - Description:  Relocate and replace existing 3” water and backflow assembly. 
 - Cause: Outside Agency – Palm Beach County Water Utility District (PBCWUD) 
 - Justification: The existing water meter had to be re-located due to a conflict with the new covered walkway. The as-built drawings did not correctly identify the location of the existing water meter.  The PBCWUD requested that the water meter be moved to a location where it would be accessible. 
   
Financial Impact: 
The Financial Impact to the Project’s Budget is $56,966.00. 
  
The source of funds is Capital Contingency.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches  
Attachments (list): 
Liberty Park ES Budget History.pdf 
Liberty Park ES Site Plan.pdf 
Liberty Park ES Data Panel.pdf 
Liberty Park ES CSR Analysis.pdf 
Liberty Park ES Facility List.pdf 
						 
					 |