						 Title: PM6 Seminole Ridge Community High Recommendation: 
I recommend the School Board approve Project Modifications in the amount of $18,000.00 for Seminole Ridge Community High School (02-NNN), CM@Risk Project #3861-8292, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description: This project modification contains the following item: 
  
- Additional Architectural Services in the amount of $18,000.00. 
 - Description:  Provide design for a second elevator.  The scope of work includes all architectural, structural, civil and MEP design. 
 - Cause:  School District Requested 
 - Justification:  The school presently has one elevator.  Because of the size of the campus, the travel time from a 1st floor location to the elevator and then to a 2nd floor location (or vice versa) can be excessive. Only one elevator was required by code.  
 - Construction costs are estimated to be $400,000.00.
   
Financial Impact: 
The financial impact to the Project's Budget is $18,000.00 
  
The source of funds is Minor Projects.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches  
Attachments (list): 
Seminole Ridge HS Budget History.pdf 
Seminole Ridge HS Site Plan.pdf 
Seminole Ridge HS Data Panel.pdf 
Seminole Ridge HS CSR Analysis.pdf 
Seminole Ridge HS Facility List.pdf 
Q&APM6.doc 
						 
					 |