Construction Management at Risk Services required for Phase 2 final construction of a 122,966 GSF, 960 student station, K-5 elementary school. The new school shall be constructed to allow for the future addition of a 1,300 student capacity middle school facility. Construction of the elementary school will be in accordance with Educational Specifications approved by the Board April 19, 2006.
Estimated Construction Budget: $19,418,653. (Five Year Capital Plan)
COP 2007B Construction Budget: $24,423,481.
Number of Stories: Two
Construction Type: Tilt-Wall
Gross Square Feet: 130,696
Budgeted Total Construction Cost per Gross Square Foot: $187. (per COP 2007B Construction Budget0
Total Actual Construction Cost per Gross Square Foot: $188.
Building Only Cost per Gross Square Foot (Div 3-16): $126.
Student Stations: 960
Budgeted Total Construction Cost per Student Station: $25,441. (per COP 2007B Construction Budget)
Total Actual Construction Cost per Student Station: $25,539.
Building Only Cost per Student Station (Div. 3-16): $17,112.
Preconstruction Fee: $199,210.
Phase 1 GMP (Site/Utilities) $1,173,957.
Phase 2 GMP (Final) $23,144,463.
Total Actual Construction Cost: $24,517,630.
Building Only Cost (Div. 3-16): $16,427,542.
Minority Sub-contractor Participation: 18.9 %