Title: PM11 Panther Run ES Project Modifications Recommendation:
I recommend the School Board approve Project Modifications in the Not-to-Exceed amount of $322,921.00 and the addition of two hundred sixty two (262) non-compensable days and one hundred nineteen (119) compensable days for Panther Run Elementary, Classroom Addition Project #2161-8378, and authorize the Chairman and Superintendent to execute all related contract documents.
Description:
This project modification contains the following items:
Item #1
CCD #4 in the amount of $279,050.00 and the addition of 179 non-compensable days.
- Item #1 in the Not-to-Exceed amount of $182,400.00 and the addition of one hundred seventy nine (179) non-compensable days and seventy eight (78) compensable days.
- Description: Extend substantial completion two hundred fifty seven (257) days.
- Cause: Unforeseen Conditions.
- Justification: Delays due to existing conditions creating revisions for conflicts with; utilities, structural components, fire stopping, mechanical, electrical and plumbing.
- Item #2 in the Not-to-Exceed amount of $96,650.00 and the addition of eighty three (83) non-compensable days and forty one (41) compensable days
- Description: Extend substantial completion one hundred twenty four (124) days.
- Cause: Design Omissions.
- Justification: The addition to the cafeteria building encroached on the existing Flammable storage and FP&L vault building creating an enclosed corridor between the two buildings. A new flammable storage area is required and the FP&L vent is required to be relocated. The Physical Education Building required an additional concrete retaining wall and dewatering system to compensate for an elevation error.
Item #2
- CCD#5 in the Not-to-Exceed amount of $13,341.00
- Description: Modify the venting of the Florida Power and Light vault.
- Cause: Design Omission
- Justification: The existing louver now opens into a covered corridor. Code requires the venting to be directly to the outside.
Item #3
- CCD#6 in the Not-to-Exceed amount of $5,456.00
- Description: Extend the mechanical room walls to the roof deck.
- Cause: Design Omission
- Justification: Code requires mechanical room wall to extend to the roof deck or to be or to be protected by fire sprinklers.
Item #4
- CCD#7 in the Not-to-Exceed amount of $25,074.00
- Description: Relocate Flammable Storage room.
- Cause: Design Omission
- Justification: The existing flammable storage room now opens into a covered corridor. Code requires flammable storage areas to open directly to the outside.
Financial Impact:
The Financial Impact to the Project’s Budget is a Not-to-Exceed of $322,921.00.
The source of funds is Restricted Reserve.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches