This project modification contains the following items
Item #1
- CCD #2 in the amount of $78,666.43
Description: Furnish and install lightning protection
Cause: School District Requested
Justification: Lightning protection is required but was not on the drawings for the added mechanical rooms, new chiller building and modular addition.
Description: Add vestibules between classroom bathrooms in the new building addition
Cause: School District Requested
Justification: The vestibules were not in the original design at time of contract. They were added to create the link between classrooms and restrooms.
Description: Added cost for the intercom above the initial $45,000
Cause: School District Requested
Justification: The contract with Suffolk included an allowance of $45,000 for the intercom. The work was an unknown scope at the time of award of contract.
Description: Permit fees to PBCWUD, LWDD and SFWMD
Cause: Outside Agency
Justification: Contractor paid the permit fees to expedite the work
required.
Item #2
§ CCD #3 in the amount of $49,148.64
§ Description: Furnish and Install ITV in the new building addition.
§ Furnish and install projector cabling in the existing school. Add gypsum board to the roof system per Building Department comments.
§ Cause: School District Requested
§ Justification: To meet the Building Department requirements (gypsum board) and the School District requirements (projectors and ITV).
Item #3
- CCD #4 in the amount of $133,991.00
- Description: Furnish and install added ceiling mounted motion sensors and wall switches with integral motion sensors.
- Cause: School District Requested
- Justification: To meet the Building Code and the Building Department requirements and the School District requirements.
Item #4
- CCD #5 in the amount of $19,287.42
- Description: Security Guard during Phase I of the HVAC renovation.
- Cause: School District Requested
- Justification: To ensure safety requirements of the School District for the students.