Construction Management @ Risk Services required for Phase 2 final construction of a 45,052 gross square foot, 500 student station classroom addition at Banyan Creek Elementary School in accordance with permitted design documents and the Educational Specifications approved by the Board on July 19, 2006.
Estimated Construction Budget: $10,526,965. (Five Year Capital Plan)
Number of Stories: One
Construction Type: CMU
Gross Square Feet: 45,052
Budgeted Total Construction Cost per Gross Square Foot: $ 234.
Total Actual Construction Cost per Gross Square Foot: $233.(Phase 1 & 2)
Building Only Cost per Gross Square Foot (Div 3-16): $157. (Phase 1 & 2)
Student Stations: 500
Budgeted Total Construction Cost per Student Station: $21,054.
Total Actual Construction Cost per Student Station: $21,013. (Phase 1 & 2)
Building Only Cost per Student Station (Div. 3-16): $13,090. (Phase 1 & 2)
Preconstruction Fee: $66,160.87
GMP Phase 1 (Site/Utilities): $592,941.00
GMP Phase 2 (Final): $9,847,250.00
Total $10,506,351.87 (Phase 1 & 2)
Building Only Cost (Div. 3-16): $6,544,920.00 (Phase 1 & 2)
Minority Sub-contractor Participation: 17.6 %