Construction Management at Risk Services required for Phase 2 Final construction of an approximately 145,000 gross square feet, 564 student station Pre-K through 12 ESE replacement school. The replacement facility will be constructed on the current site followed by demolition of the existing facility and construction of playfields and auxiliary facilities in accordance with the Educational Specifications approved by the Board on March 16, 2005.
Board Approved Amended Construction Budget: $35,409,743.
Number of Stories: One
Construction Type: Concrete Block
Gross Square Feet: 145,000
Budgeted Total Construction Cost per Gross Square Foot: $244.
Total Actual Construction Cost per Gross Square Foot: $218. (Phase 1 & 2)
Building Only Cost per Gross Square Foot (Div 3-16): $146. (Phase 1 & 2)
Student Stations: 564
Budgeted Total Construction Cost per Student Station: $62,783.
Total Actual Construction Cost per Student Station: $56,099. (Phase 1 & 2)
Building Only Cost per Student Station (Div. 3-16): $37,559. (Phase 1 & 2)
Preconstruction Fee: $250,740.
GMP Phase 1: $1,016,265. (Utility Relocation)
GMP Phase 2: Final $30,373,079.
Total Actual Cost of Construction: $31,640,084.
Building Only Cost (Div. 3-16): $21,183,544. (Phase 1 & 2)
Minority Sub-consultant Participation: 18.2%