Title: CP-8 Amend the CM Agreement for Wellington High School Auditorium Recommendation:
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement to establish the Guaranteed Maximum Price (GMP) for construction in the amount of $11,488,722.42 to The Weitz Company, LLC, for Wellington High School Auditorium, Project No: 2191-8272 and authorize the Superintendent and Board Chairman to sign all required documents.
Description: Construction Management @ Risk Services required for construction of an approximately 21,155 GSF Auditorium in accordance with the Educational Specifications approved by the Board on February 2, 2002.
Estimated Construction Budget: $10,778,502. (Five Year Capital Plan)
Number of Stories: Two
Construction Type: Tilt-Wall
Gross Square Feet: 21,155
Budgeted Total Construction Cost per Gross Square Foot: $510.
Total Actual Construction Cost per Gross Square Foot: $545.
Building Only Cost per Gross Square Foot (Div 3-16): $391.
Student Stations: NA
Budgeted Total Construction Cost per Student Station: NA
Total Actual Construction Cost per Student Station: NA
Building Only Cost per Student Station (Div. 3-16): NA
Preconstruction Fee: $40,300.00
GMP: $11,488,722.42
Total Cost of Construction: $11,529,022.42
Building Only Cost (Div. 3-16): $8,267,751.
Minority Sub-contractor Participation: 25.6 %
Financial Impact:
The financial impact is a commitment of $11,573,739.42 which includes the GMP of $11,488,722.42 and $85,017. for the District provided Builder’s Risk Insurance. The source of funds is the corresponding Capital Project Budget, and Construction Contingency.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)
Attachments (list):
Beneficial.pdf
PPE.pdf
Facility Summary.pdf
CSA Table p3.pdf
Data Panel.pdf
ExeAgr.pdf
GMP Exh Z.pdf
Amendment.pdf
Checklist.pdf
|