Calusa ES HVAC Replacement Project No. 1911-8222
 
This project modification contains the following items:
 
Item #1
§         CCD #3R in the amount of $4,502.00.    
§        Description: Provide additional temporary air conditioning. 
§         Cause: Design Omission
§         Justification:  The engineering estimate for temporary air conditioning capacity (Tons) was not adequate for cooling the main office during the construction.  One additional month of temporary air conditioning was required.
 
Item #2
§         CCD #20R in the amount of $7,025.00
§         Description:  Install four additional heat detectors, Rooms 212, 207,106, and 110.
§         Cause: School District Requested.
§         Justification:  Requested by the Building Department inspector upon final review of the facility.
 
Item #3
§         CCD #21M in the amount of $1,301.00.
§         Description:  Install a double layer of drywall at roof truss and rated wall.
§         Cause: Unforeseen Condition.
§         Justification: The roof truss was placed directly over a wall that required a 4-hour fire rating.  The concrete wall encased the roof truss and therefore did not comply with the 4 hour fire rating criteria.  The engineered solution was the installation of drywall on either side of the wall.
 
Item #4
§         CCD #22 in the amount of $12,805.00.
§         Description:  Correct above ceiling electrical code violations and firewall penetrations.
§         Cause: School District Requested.
§         Justification: Corrections required prior to acoustical ceiling installation and Building Department inspections and approvals.
 
Item #5
§         CCD #23 in the amount of $2,133.00  
§         Description:  Remove and replace PVC roof vent line and 3” copper water main.  Drain, re-fill and bleed water system.       
§         Cause: Unforeseen Condition. 
§         Justification:  Existing vent stack was located too close to the make up air intake.  The 3” copper main conflicted with the installation of ductwork.  
 
Item #6
§      Description: On Calusa Elementary School, the Contractor, Hill York Services, achieved Substantial Completion on January 26, 2004, and requested a Reduction of Retainage from 5% to 1%; the Architect and District staff recommends this reduction.