This project will consist of Construction Management at Risk Services required for construction of additional classrooms, core facilities and infrastructure for the addition of a 43,636 GSF middle school with 413 proposed student stations and 36,910 GSF high school classrooms and core facilities with 345 proposed student stations.
A
Approved Construction Budget: $14,269,498.
Minority Participation: 15%
No. of Stories: To be determined during Preconstruction Phase
Construction Type: To be determined during the Preconstruction Phase
Gross Square Feet: 80,546
Construction Cost Per Gross Square Foot: $177.16
Total Student Stations: 758
Construction Cost Per Student Station: $18,825.20
Preconstruction Phase Fee: $45,520.
Reimbursable Expenses: $27,700.
Total: $73,220.