						 Title: CP-5 Amend CM Agreement for Glades Central High Academy Recommendation: 
I recommend the School Board revise the project budget to $9,577,320 and approve an Amendment to the Construction Management at Risk Agreement to establish the Guaranteed Maximum Price (GMP) for construction in the amount of $7,173,596. to W.G. Mills, Inc., for Glades Central High  Academy Project No. 2301-8316 and authorize the Superintendent and Board Chairman to sign all required documents.  
Description: Construction Management at Risk services required for facility modifications and academic program changes for Glades Central High School. Construction of a new classroom building to accommodate the additional programs. Construction will be in accordance with the Educational Specifications approved by the Board on March 16, 2005.    
  
Estimated Construction Budget: $4,261,031  
                                               
Number of Stories: Two 
Construction Type: Concrete Masonry Block 
  
Gross Square Feet: 32,859  
Budgeted Construction Cost per Gross Square Foot: $130. 
Total Construction Cost per Gross Square Foot: $220. 
Building Cost per Gross Square Foot (Div 3-16): $192. 
  
Student Stations: 164 
Budgeted Construction Cost per Student Station: $25,982 
Total Construction Cost per Student Station: $44,021. 
Building Cost per Student Station (Div. 3-16): $38,429. 
  
Preconstruction Fee:                     $45,855. 
GMP:                                       $7,173,596. 
  
Total Cost of Construction:     $7,219,451. 
  
Building Cost (Div. 3-16):      $6,302,444. 
  Minority Sub-contractor Participation: 17.6 %     
Financial Impact: 
The financial impact is an increase to the Project Budget of $4,077,320 and a commitment of $7,226,681. which includes the GMP of $7,173,596 and $53,085. for the District provided Builder’s Risk Insurance. The source of funds is the Capital Project Budget and Capital Contingency.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us)  
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)  
Attachments (list): 
Budget Revision Summary.xls 
BENE MILLS.pdf 
PPE WGMILLS.pdf 
Glades_ED SPEC.pdf 
Chap4.1.pdf 
GCHS Data Panel.pdf 
GCHS Site.pdf 
ExeAgrGCHS.pdf 
GMP PROPOSAL.pdf 
GCHS GMP AMENDMENT.pdf 
Checklist.pdf 
Q&ACP5.doc 
						 
					 |