Construction Management @ Risk Services required for Phase 1 construction of a 41,699 gross square foot, 500 student station classroom addition at Banyan Creek Elementary School in accordance with permitted design documents and the Educational Specifications approved by the Board on July 19, 2006.
Estimated Construction Budget: $10,526,965. (Five Year Capital Plan)
Number of Stories: Two
Construction Type: Tilt Wall
Gross Square Feet: 41,699
Budgeted Total Construction Cost per Gross Square Foot: $ 252
Total Actual Construction Cost per Gross Square Foot: NA (Phase 1 only)
Building Only Cost per Gross Square Foot (Div 3-16): NA (Phase 1 only)
Student Stations: 536
Budgeted Total Construction Cost per Student Station: $19,640.
Total Actual Construction Cost per Student Station (Div. 3-16): NA (Phase 1 only)
Building Only Cost per Student Station (Div. 3-16): NA (Phase 1 only)
Preconstruction Fee: $66,160.87
GMP Phase 1: (Site/Utilities) $592,941.00
Total $659,101.87
Building Only Cost (Div. 3-16): NA (Site work only)
Minority Sub-contractor Participation: 8.2% (Phase 1 Site/Utilities work)