Construction Management @ Risk Services required for Phase 2 final construction of a 119,668 gross square foot, 745 student station K-5 replacement school with core facilities to accommodate 960 students, in accordance with the Educational Specifications approved by the Board on May 17, 2006.
Estimated Construction Budget: $22,475,056. (Five Year Capital Plan)
Number of Stories: Two
Construction Type: Tilt-Wall
Gross Square Feet: 119,668
Budgeted Total Construction Cost per Gross Square Foot: $188.
Total Actual Construction Cost per Gross Square Foot: $187. (Phase 1 & 2)
Building Only Cost per Gross Square Foot (Div 3-16): $164. (Phase 1 & 2)
Student Stations: 745
Budgeted Total Construction Cost per Student Station: $30,168.
Total Actual Construction Cost per Student Station: $30,110. (Phase 1 & 2)
Building Only Cost per Student Station (Div. 3-16): $26,322. (Phase 1 & 2)
Preconstruction Fee: $157,395.
Phase 1 GMP (Demolition): $975,118.
Phase 2 GMP (Final): $21,299,768.
Total Cost of Construction: $22,432,281. (Phase 1 & 2)
Building Only Cost (Div. 3-16): $19,609,808. (Phase 1 & 2)
Minority Sub-contractor Participation: 26 %