Construction Management at Risk services required for the construction of a 129,900 GSF elementary school with related facilities and an adjacent 15,000 GSF facility to be utilized as an Environmental Studies Center by Florida Atlantic University. 
 
Estimated Construction Budget: $21,511,247.
                                              
Number of Stories: Two
Construction Type: Tilt-Wall
 
Gross Square Feet: 144,815
Budgeted Construction Cost per Gross Square Foot: $149 
Total Construction Cost per Gross Square Foot: $NA 
Building Cost per Gross Square Foot (Div 3-16): $ NA
 
Student Stations: 1000
Budgeted Construction Cost per Student Station: $21,511.
Total Construction Cost per Student Station: $ NA
Building Cost per Student Station (Div. 3-16): $ NA
 
Preconstruction Fee:                        $322,185.
Phase 1 GMP (Site/Utilities):       $5,902,176.
 
Total Cost of Construction:     $NA
 
Building Cost (Div. 3-16):      $3,059,000.
 
Minority Sub-contractor Participation: 14 % (This is Phase 1 of a two phase project. The overall goal for participation is established at 15%.)