						 Title: CP-7 Amend CM Agreement for Palm Beach Gardens Elementary Modernization Recommendation: 
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement to establish the Final Guaranteed Maximum Price (GMP) for construction in the amount of $23,394,807. to C.R. Klewin Southeast, Inc., for Palm Beach Gardens Elementary Modernization, Project No: 0111-7505 and authorize the Superintendent and Board Chairman to sign all required documents.    
Description: Construction Management @ Risk Services required for replacement of the existing Pre K-5 facility with a 121,000 GSF facility to accommodate 970 student stations. The replacement facility will be constructed on the current site. Students will be relocated during construction. Construction will be in accordance with the Educational Specifications approved by the Board on July 20, 2005.   
  
Estimated Construction Budget: $24,597,580.  
                                               
Number of Stories: Two 
Construction Type: Tilt-Wall 
  
Gross Square Feet: 121,000 
Budgeted Construction Cost per Gross Square Foot: $203. 
Total Construction Cost per Gross Square Foot: $195. 
Building Cost per Gross Square Foot (Div 3-16): $162.  
  
Student Stations: 970 
Budgeted Construction Cost per Student Station: $25,358. 
Total Construction Cost per Student Station: $24,275. 
Building Cost per Student Station (Div. 3-16): $ 20,258. 
  
Preconstruction Fee:                     $159,539. 
GMP:                                       $23,394,807. 
  
Total Cost of Construction:     $23,554,346. 
  
Building Cost (Div. 3-16):      $ 19,650,287. 
  Minority Sub-contractor Participation: 15.7 %    
Financial Impact: 
The financial impact is a commitment of $23,567,929. which includes the GMP of $23,394,807. and $173,122. for the District provided Builder’s Risk Insurance. The source of funds is the corresponding Capital Project Budget. 
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us)  
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)  
Attachments (list): 
BeneKlewin.pdf 
PPE KLEWIN.pdf 
PBGES  ED SPEC.pdf 
Chap4.1.pdf 
PBGEL Data Panel.pdf 
SITEPLAN.pdf 
ExeAgree-PBGES.pdf 
GMP Proposal.pdf 
PBG ES GMP AMENDMENT.pdf 
Checklist.pdf 
Q&ACP7.doc 
						 
					 |